Making news

Cat Linh – Ha Dong metro line to begin commercial operation from May 1

Hanoi’s first metro service running from Cat Linh to Ha Dong will start commercial operation from May 1 as directed by the Prime Minister.

Safety problems in the project have been removed, according to a report from the Ministry of Transport, adding ACT – French safety consultants – which is hired to oversee the final stages of the metro project – is expected to complete safety certification for the railway on April 28.

Travel on the Cat Linh – Ha Dong Urban Railway will be free for the first 15 days of operation.
After that, a one-way ticket will cost 15,000 VND (0.65 USD). Then, the operation unit will notify passengers of the price of monthly and quarterly tickets soon.

The Cat Linh – Ha Dong Urban Railway project started in 2008 with a total investment of 18 trillion VND (782.6 million USD) and was initially expected to be completed in 2016. However, it has missed its completion deadline several times.

The Cat Linh – Ha Dong line runs 13.5km with 12 stations, encompassing Cat Linh, La Thanh, Thai Ha, Lang, Thuong Dinh, Ring Road 3, Phung Khoang, Van Quan, Ha Dong, La Khe, Van Khe and Yen Nghia.

Meanwhile, Management Authority for Urban Railways Ho Chi Minh City said that two three-car trains and four six-car trains for the first metro line (Metro Line 1) in the southern hub are expected to arrive in the city between May and July.

The two three-car trains will be shipped from Japan on May 1 and reach Ho Chi Minh City in nine days. The remainders will be delivered to the city in June and July.

The trains will be on trial run from Quarter 4 this year. Within the same time, other tasks like operations, training, technology transfer, and examination will be in progress.

Metro Line 1, which is 20 kilometres long with 3 sub-stations and 11 stations, is 83 percent complete and is expected to officially open for use in 2022. It is built at the total cost of more than 43.7 trillion VND.
VNA/VNP


Top